SW Boeckman Rd between SW Stafford Rd and SW Canyon Creek Rd

Construction - Closed
Direction Impacted
Both
Comments

Ongoing construction on SW Boeckman Rd between SW Stafford Rd and SW Canyon Creek Rd. Full closure in both directions until April 2025.

Public Contact
Zach Weigel
City of Wilsonville
Phone: (503) 570-1565
Email: weigel@ci.wilsonville.or.us
Event Id
3786
Updated
1/22/2024 7:46 AM

SW 65th Ave and SW Stafford Rd

Construction - Moderate Impact
Direction Impacted
Both
Comments

A construction signal has been installed at the intersection of SW 65th Ave and SW Stafford Road starting in November 2023. Expect intermittent delays.

Public Contact
Zach Weigel
City of Wilsonville
Phone: (503) 570-1565
Email: weigel@ci.wilsonville.or.us
Event Id
3673
Updated
11/07/2023 3:15 PM

Denney Rd to Merry Ln nightwork

Construction - Moderate Impact
Comments

Expect lane restrictions, alternating traffic patterns, flaggers in use, sidewalk closures. Work hours generally 7 pm to 5 am Sunday through Friday morning.

Public Contact
David Marciniak
Willamette Water Supply Program
Phone: (503) 941-4570
Email: info@ourreliablewater.org
Event Id
4098
Updated
4/12/2024 11:12 AM

Murray Blvd to Teal Blvd nightwork

Construction - Moderate Impact
Comments

Lane restrictions, flaggers at intersections, no right-hand-turns through worksite. Work hours are generally from 8 p.m. to 5 a.m. Monday through Friday morning. Crews will work in 400‐foot sections, and incrementally move from east to west with the pipeline, then work on smaller tasks after the pipe is installed.

Public Contact
David Marciniak
Willamette Water Supply Program
Phone: (503) 941-4570
Email: info@ourreliablewater.org
Event Id
4097
Updated
4/12/2024 11:05 AM

Scholls Ferry Rd, Roy Rogers to Murray

Construction - Moderate Impact
Comments

Expect lane restrictions for drinking water pipeline construction. 6:30 am to 5:30 pm Monday through Friday, with the exception of work at most intersections and other potential activities scheduled for nighttime work.

Public Contact
David Marciniak
Willamette Water Supply Program
Phone: (503) 941-4570
Email: info@ourreliablewater.org
Event Id
4024
Updated
4/12/2024 10:49 AM

Kinsman Road southbound lane closure

Construction - Moderate Impact
Comments

SW Kinsman Road Lane Closure

Beginning March 1, 2024

SW Kinsman Road between SW Wilsonville Road and SW Barber Street


Work will soon get underway to restore permanent concrete paving on SW Kinsman Road between SW Wilsonville Road and SW Barber Street for the Willamette Water Supply Program pipeline project. This work is planned to occur in stages, with temporary traffic control changing as work moves through the area to maintain safety and limit disruptions to businesses and the traveling public.


Anticipated Schedule: March 1, 2024 – June 2024


Traffic Impact: The southbound lane of SW Kinsman Road will be closed from SW Barber Street to just north of the TVFR Fire Station.


Note: This schedule is subject to change based on weather and other conditions.

Public Contact
Marlys Mock
Willamette Water Supply Program
Phone: (503) 941-4570
Email: info@ourreliablewater.org
Event Id
4056
Updated
2/26/2024 9:50 AM

NB lane of SW 95th Ave between SW Boeckman Rd and SW Hillman Ct

Construction - Moderate Impact
Comments

Willamette Water Supply Program Wilsonville Area Pipeline Project Northbound Lane Closure between SW Boeckman Road and SW Hillman Court for pipeline construction and street restoration.


The northbound lane of SW 95th Avenue between SW Boeckman Road and SW Hillman Court will be closed during construction. Northbound traffic will be detoured to SW Boones Ferry Road. Traffic detour signage and flaggers will be used during the closure.  

Public Contact
Marlys Mock
Willamette Water Supply Program
Phone: (503) 941-4570
Email: info@ourreliablewater.org
Event Id
4049
Updated
2/20/2024 10:25 AM

Western Avenue limited closure, local access only

Construction - High Impact
Direction Impacted
Both
Comments

Beaverton Hillsdale Highway will be restricted to two lanes of traffic, one eastbound and one westbound, between Western Avenue and Jamieson Road from January 2nd through April 30 for pipeline construction. Western Avenue local access only for northbound traffic with single lane open for southbound traffic. Business access open.

Project website: www.beavertonoregon.gov/trafficalerts

Public Contact
David Marciniak
Willamette Water Supply Program
Phone: (503) 941-4570
Email: info@ourreliablewater.org
Event Id
3891
Updated
12/29/2023 6:18 PM

Beaverton Hillsdale Highway lane restrictions

Construction - High Impact
Direction Impacted
Both
Comments

Beaverton Hillsdale Highway will be restricted to two lanes of traffic, one eastbound and one westbound, between Western Avenue and Jamieson Road from January 2nd through April 30 for pipeline construction. Western Avenue local access only for northbound traffic with single lane open for southbound traffic. Business access open.

Project website: www.beavertonoregon.gov/trafficalerts

Public Contact
David Marciniak
Willamette Water Supply Program
Phone: (503) 941-4570
Email: info@ourreliablewater.org
Event Id
3890
Updated
12/29/2023 6:14 PM